Analysis and Research on Typical Problems in Commissioning of Ventilation and Air Conditioning Systems in Metro Stations
- DOI
- 10.2991/978-94-6463-902-5_37How to use a DOI?
- Keywords
- Ventilation and air conditioning system; system commissioning; metro station; cooling water system; IBP panel; modulating motorized damper; fault analysis
- Abstract
Commissioning of ventilation and air conditioning (HVAC) systems in metro stations is essential for operational readiness but faces significant challenges, including tight schedules, high workloads, and frequent failures. This paper analyzes three typical commissioning issues encountered in a provincial capital metro project: (1) cooling water return failure in deeply buried stations, (2) malfunction of manual smoke exhaust fan control via the Integrated Backup Panel (IBP), and (3) ambiguous intermediate position settings for modulating motorized dampers. Combining theoretical analysis with on-site measurements, the root causes are identified, and validated solutions are proposed. Key corrective measures include installing pressure-gauge-equipped air vents at pipeline high points, redesigning pipe elevation differences to prevent air entrapment, implementing integrated fan-damper control logic with hardware interlocks, and determining damper positions through on-site airflow calibration. These solutions effectively resolved the specific issues and offer actionable guidance for commissioning similar metro HVAC systems.
- Copyright
- © 2025 The Author(s)
- Open Access
- Open Access This chapter is licensed under the terms of the Creative Commons Attribution-NonCommercial 4.0 International License (http://creativecommons.org/licenses/by-nc/4.0/), which permits any noncommercial use, sharing, adaptation, distribution and reproduction in any medium or format, as long as you give appropriate credit to the original author(s) and the source, provide a link to the Creative Commons license and indicate if changes were made.
Cite this article
TY - CONF AU - Sun Li PY - 2025 DA - 2025/12/16 TI - Analysis and Research on Typical Problems in Commissioning of Ventilation and Air Conditioning Systems in Metro Stations BT - Proceedings of the 2025 7th International Conference on Civil Engineering, Environment Resources and Energy Materials (CCESEM 2025) PB - Atlantis Press SP - 380 EP - 386 SN - 2352-5401 UR - https://doi.org/10.2991/978-94-6463-902-5_37 DO - 10.2991/978-94-6463-902-5_37 ID - Li2025 ER -